BHE Sagebrush Substation

  • Project Manager: Bruce Rall
  • Superintendent: Caleb Baumeister/Lee Jacobson
  • Owner: Black Hills Energy
  • Project Location: Newcastle, WY
  • Contract Amount: $424,849.00
  • Start Date: 10/15/18
  • Completion Date: 3/25/19

Project consisted of 10 circuit breaker pads, 1 building, 1 transformer pad, 141 drilled piers from sizes of 30" to 60" ranging 25 feet in depth.




 
 