Crestwood Station 8 Substation

  • Project Manager: Bruce Rall
  • Superintendent: Tim Voneye
  • Owner: McKenzie Electric
  • Project Location: Watford City, North Dakota
  • Contract Amount: $308,139.50
  • Start Date: 7/30/2018
  • Completion Date: 9/1/2018

This project consisted of 8 circuit breaker pads, 1 building, 1 transformer pad, 50 drilled piers from sizes of 36" to 60" ranging 40 feet in depth.




 
 