Wanblee Substation, Stage 01

  • Project Manager: Bruce Rall
  • Superintendent: Jerry Vanden Bos
  • Owner: Western Area Power Administration
  • Project Location: Wanblee, SD
  • Contract Amount: 670,000
  • Final Contract Amount: 725,000
  • Start Date: September 6, 2017
  • Completion Date: May 4, 2018

Wanblee Substation, Stage 01, Work was done for Western Area Power Administration.
Scope of Work: Site development, embankments and drains, concrete foundations, fence, below ground conduits and grounding.




 
 