Watford City Substation MDU

  • Project Manager: Bruce Rall
  • Superintendent: Caleb Baumeister
  • Owner: "MDU" Montana Dakota Utilities
  • Project Location: Watford City, North Dakota
  • Contract Amount: $455,642.34
  • Start Date: 7-11-2018
  • Completion Date: 8-17-2018

Project consisted of 10 circuit breaker pads, 1 building, grade beam with 3 stoops, 1 transformer pad with containment walls, 120 drilled piers from sizes of 36" to 60" ranging 25 feet in depth. Some of the piers had to use drilling fluids.




 
 