2011 East Anamosa Street
|
E. Anamosa St. consisted of the complete reconstruction of 4 blocks of city streets. Subcontractors installed new water line, sanitary sewer, services and storm sewer. Complete Concrete Inc. constructed 6,600 sy of 8” PCC Pavement (3 lanes), 21,000 sy of 6” Sidewalk, 2,500 lf of B68 & B66 C&G, 26 ea. CIP Storm Sewer Inlets along with 8” fillets, driveway approaches & driveways. Once completed the 4 blocks of reconstructed roadway greatly enhanced the area for the residence of North Rapid City.