2013 - I90, EBL, (MRM 111-122)

  • Owner: SDDOT
  • Project Location: Wall, SD
  • Contract Amount: $15,765,900

Complete Reconstruction of Interstate 90, East Bound Lanes from MRM 111 to MRM 122. 11 miles of removals, subgrade prep, grading, edge drain, 26' wide x 10.5" thick PCC Paving, asphalt shoulders and 6 exit ramps.




 
 