Complete Contracting Solutions of Rapid City, SD

605-388-0111

Drilled Foundations, Concrete Paving and General Contracting

 

West Chicago Street Reconstruction

  • Project Manager: Jay Heinrich

Complete reconstruction of West Chicago Street, from west of the Sturgis Road intersection to Sheffer Street, began in March 2018 with a completion date of June 28, 2019. Complete Concrete, Inc. of Rapid City was the prime contractor of the $9.5 million project, with 42,650 sy of PCCPaving. In conjunction with the road construction, the city of Rapid City installed new water main and sanitary sewer lines to replace old infrastructure. The construction also included bridge deck rehabilitation and bridge widening to build a sidewalk. The sidewalk was constructed along the entire length of the project.




 
 
© 2020 Complete Contracting Solutions: 7201 S. Hwy 16 Suite 100, Rapid City, SD 57702 605-388-0111 Fax: 605-388-6139