St. Francis Substation

  • Project Manager: Bruce Rall
  • Superintendent: Nick Hanson
  • Owner: Rushmore Electric
  • Project Location: St. Francis, SD
  • Point of Contact: Besler, Inc.
  • Contract Amount: $411,998.77
  • Start Date: 1/4/19
  • Completion Date: 4/7/19

Project consisted of 2 circuit breaker pads, 1 building, 1 transformer pad, 74 drilled piers from sizes of 30" to 72" ranging 25 feet in depth.




 
 